Skip Navigation LinksINVITATION-NOTICE-FOR-THE-PRE-QUALIFICATION-OF-APPLICANTS-FOR-ENGINEERING,-PROCUREMENT-AND-CONSTRUCTION-OF-REHABILITATION-W

 INVITATION NOTICE FOR THE PRE-QUALIFICATION OF APPLICANTS FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION OF REHABILITATION WORKS OF KAMOJANG GEOTHERMAL POWER PLANT UNIT 2 AND 3

INVITATION

NOTICE FOR THE PRE-QUALIFICATION OF APPLICANTS FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION OF REHABILITATION WORKS OF KAMOJANG GEOTHERMAL POWER PLANT UNIT 2 AND 3

 

The Kamojang Geothermal Power Plant Unit 2 and 3 (2 x 55 MW) which was commissioned in 1987, the power plant has been in operating for over 30 years and is nearing the end of their design life. PT. Indonesia Power (IP) has received a loan from KfW, a German state-owned development bank towards the cost for this rehabilitation project. IP wishes to select potential bidders to rehabilitate and modernize Unit 2 and 3 to extend their economic and technical life for up to 25 years whilst improving plant performance, efficiency and reliability.

The planned rehabilitation and modernization works for Kamojang Unit 2 & 3 includes mechanical, electrical, control & instrumentation work for the main plant and equipment such as steam turbines, generators, cooling tower, vent station, control system and instrumentation.

This Pre-Qualification is open to interested party or parties who have previous experience in implementing power generation projects and will be selected through a competitive bidding process from a pool of Applicants that meet the qualification criteria set forth in Pre-Qualification Document. The Qualification Criteria will be based on certain categories which shall represent the Applicant's ability to undertake the rehabilitation of power plant, its power generation experience and its financial strength.

IP invites interested parties to submit Pre-Qualification application in accordance with the criteria set forth in the Pre-Qualification Document. Only Applicants which Qualification Statements demonstrate that they meet all of the Qualification Criteria set forth in the Pre-Qualification Document will be shortlisted and invited to submit a bid proposal for the project.

Pre-Qualification Document may be collected on August 6, 2019 until the submission date at the following hours: 09.00 am until 03.00 pm West Indonesia Standard Time.

At the following address:

PT INDONESIA POWER

DIVISION OF SPARE PARTS AND SERVICES PROCUREMENT,

CENTENNIAL TOWER, 8th FLOOR, LOT E

JALAN JEND. GATOT SUBROTO KAV. 24-25 - JAKARTA 12950

fachransjah@indonesiapower.co.id

 

Applicant should submit to IP, their application for the Pre-Qualification during normal business hours at or before 04.00 pm West Indonesia Standard Time on or before September 5, 2019. Late application will be returned unopened to the Applicants.

Jakarta, August 1, 2019

PT INDONESIA POWER

VICE PRESIDENT OF SPARE PARTS AND SERVICES PROCUREMENT





Komentar:

Berita Lainnya

  • Bangun Pembangkit Terapung, PT Indonesia Power Kerjasama dengan PT PAL

  • Lagi, Indonesia Power Sabet 2 Penghargaan Subroto Award

  • Tingkatkan Kompetensi Operation dan Maintenance, AKOME Jilid 4 Digelar